Eggborough Power Station – DSM Demolition Ltd
PPS Metal Recycling (PPS) were appointed by DSM Demolition Ltd
(DSM) as a sub‐contractor for associated works at their site of
Eggborough Power Station. PPS undertook the following works:
- Dismantle and Processing of Large and Small Transformers.
- Clearance of re‐usable pipe work
- Internal Strip‐out of stores
- Dismantle and lifting operations for the Alternator within
the Turbine Hall.
- Dismantle and lifting operations for the Pump House
including the removal of overhead gantry crane
- Purchasing of ferrous and non‐ferrous metals.
/li>
Works were undertaken in a phased sequence under programme
timescales. All co‐ordination between PPS and DSM on a regular
basis.